| LIST OF RECENTLY COMPLETED PROJECTS | ||||
| ( YEAR 2005 ) | ||||
| NO | CLIENT | DESCRIPTION OF WORKS | CONTRACT SUM | Month / Year |
| RM | ||||
| 1 | Kota Selatan Indah | Proposed Road and Surface Water Drainage Works | 2,000,000.00 | Jan 05 |
| Sdn Bhd | to Phase 3A, Mukim Rawang, Selangor | |||
| 2 | Kota Selatan Indah | Proposed Road and Surface Water Drainage Works | 2,000,000.00 | Jun 05 |
| Sdn Bhd | to Phase 3B, Mukim Rawang, Selangor | |||
| 3 | Perbadanan | Substation/Genset Room, Elevated water Tank c/w | 4,000,000.00 | Jun 05 |
| Kemajuan Pertanian | Pump Equipment & Sewage Treatment Plant | |||
| Selangor | ||||
| 4 | Pembinaan Sri Jati | Proposed External works for Cadangan Membina dan | ||
| Sdn Bhd | menyiapkan 52 unit Rumah Bungalow, Bukit Rahman | 2,000,000.00 | 2005 | |
| Putra, Sg.Buloh, Selangor. | ||||
| 5 | SPPK Sdn Bhd | Main Drain and Ancillary works for Pembangunan | ||
| Skim Perumahan Diatas Lot PT5281 (HSD83185) | 1,000,000.00 | 2005 | ||
| dan PT5282 (HSD83186) Bkt Jalil, Mk Petaling, KL | ||||
| 6 | Kota Selatan Indah | Proposed Road and Surface Water Drainage Works | ||
| Sdn Bhd | to Parcel 1, Mukim Rawang, Selangor | 3,000,000.00 | July 05 | |
| 7 | SPPK Sdn Bhd | Construction of Main Sewer Reticulation at Phase 4B | ||
| for Cadangan Pembangunan Kg Sg Midah | 1,000,000.00 | April 05 | ||
| Diatas Lot PT894-899 Mk Petaling Cheras KL | ||||
|
Total |
14,000,000.00 |
|||